Construction Journal: August 31-September 04, 2009

Sep 05

Monday, August 31, 2009

  • Electricians are installing cable trays in the sanctuary.
  • Hallways and offices are carpeted on the second floor.
  • Walls in the Dockyard are painted.

Tuesday, September 01, 2009

  • Lights in the hospitality lounge are installed.
  • Handicap washroom walls and floor are tiled.
  • Cable tray to the video production room is installed.
  • Stage platform extension is constructed.
  • Washroom sinks are installed in Infant Care, Periwinkle Pier, Tugboat Bay and Pre-school rooms.
  • The kitchen cabinets were delivered from Hubbards and are ready for installation.
  • Eastlink will have phone services installed by Sept. 11th.

Wednesday, September 02, 2009

  • Contacted Aliant Telephone for temporary service to monitor the fire alarm and elevator phone.
  • Contacted Eastlink who will provide permanent service by Wednesday Sept 9th.
  • Contacted Dave Smith (Stanley security service) for a site visit tomorrow to schedule installation on Monday or Tuesday.
  • Boardroom is now carpeted.
  • Sound control booths in Dockyard and Kings Pier have been modified for a 5′ wall.
  • Electrical wiring and metal bases for the external flood lights are ready for concrete.

Thursday, September 03, 2009

  • Mill-wrights are installing washroom cabinets and sinks.
  • Installing florescent light fixtures over the stage.
  • Coastal employees are installing interior doors on both floors.

Friday, September 04, 2009

  • Drywallers are constructing the bulkhead over the security desk in corridor 3.
  • External flood lights are ready for the fixtures.
  • Wash basin cabinets are installed in the men and women’s facilities.
  • Cable tray ceiling brackets are modified in the sanctuary.
  • Air-conditioning units are being installed in rooms 223 and 224.
  • The bookcase wall unit in the hospitality lounge is completed.