Construction Journal: August 31-September 04, 2009
Sep 05
Monday, August 31, 2009
- Electricians are installing cable trays in the sanctuary.
- Hallways and offices are carpeted on the second floor.
- Walls in the Dockyard are painted.
Tuesday, September 01, 2009
- Lights in the hospitality lounge are installed.
- Handicap washroom walls and floor are tiled.
- Cable tray to the video production room is installed.
- Stage platform extension is constructed.
- Washroom sinks are installed in Infant Care, Periwinkle Pier, Tugboat Bay and Pre-school rooms.
- The kitchen cabinets were delivered from Hubbards and are ready for installation.
- Eastlink will have phone services installed by Sept. 11th.
Wednesday, September 02, 2009
- Contacted Aliant Telephone for temporary service to monitor the fire alarm and elevator phone.
- Contacted Eastlink who will provide permanent service by Wednesday Sept 9th.
- Contacted Dave Smith (Stanley security service) for a site visit tomorrow to schedule installation on Monday or Tuesday.
- Boardroom is now carpeted.
- Sound control booths in Dockyard and Kings Pier have been modified for a 5′ wall.
- Electrical wiring and metal bases for the external flood lights are ready for concrete.
Thursday, September 03, 2009
- Mill-wrights are installing washroom cabinets and sinks.
- Installing florescent light fixtures over the stage.
- Coastal employees are installing interior doors on both floors.
Friday, September 04, 2009
- Drywallers are constructing the bulkhead over the security desk in corridor 3.
- External flood lights are ready for the fixtures.
- Wash basin cabinets are installed in the men and women’s facilities.
- Cable tray ceiling brackets are modified in the sanctuary.
- Air-conditioning units are being installed in rooms 223 and 224.
- The bookcase wall unit in the hospitality lounge is completed.