Construction Journal: July 27-31, 2009

Aug 03

Monday, July 27

  • Dexter grading and compacting the parking lot.
  • Half wall in main office completed.

Tuesday, July 28

  • More grading and compacting of the parking lot. Compaction tests show the gravel base exceeds the 100% scale for paving.

Wednesday, July 29

  • Construction has begun on the bulkhead in the fireplace seating lounge within the hospitality room.

Thursday, July 30

  • The four main electrical cables were pulled into the electrical room today. Next step after hook-up: Inspection (before being energized by NS Power).
  • Kitchen ready for inspection to ensure all services meet requirements for kitchen cabinets & equipment installation.

Friday, July 31

  • Electricians worked on connecting the main transformer to the NS Power lines.
  • Plumbing & Heating: 2 hot water furnaces being installed in the mechanical room. Gas lines being installed on the roof.
  • Corridor classroom bulkheads dry walled and pot lights installed.