Construction Journal: July 20-24, 2009

Jul 25

Monday, July 20

  • Exterior windows installed in corridor 3.
  • Fire escape stairway installed (back of church).
  • Dry wall hanging begun: children’s area, first floor.
  • Electrical equipment installation in main electrical room.

Tuesday, July 21

  • Elevator parts arrived on site.
  • Electrical room being wired for the main power supply.
  • Dexter working on the parking lot overflow area at the west end, and re-constructing the stone entrance wall.

Wednesday, July 22

  • Dexter is grading and compactng the driveway entrance to the site.
  • Work on parking area delayed due to heavy rain.  :(
  • The building is now closed up at night to prevent unauthorized persons from entering the building.

Thursday, July 23

  • Office flourescent light bulbs ordered.
  • NS Power installing the main power transformer for the church.
  • Dexter Construction is grading the driveway area in front of the church building.

Friday, July 24

  • Dry wall taping on the second floor, in preparation for painting, is completed.