Construction Journal: July 20-24, 2009
Jul 25
Monday, July 20
- Exterior windows installed in corridor 3.
- Fire escape stairway installed (back of church).
- Dry wall hanging begun: children’s area, first floor.
- Electrical equipment installation in main electrical room.
Tuesday, July 21
- Elevator parts arrived on site.
- Electrical room being wired for the main power supply.
- Dexter working on the parking lot overflow area at the west end, and re-constructing the stone entrance wall.
Wednesday, July 22
- Dexter is grading and compactng the driveway entrance to the site.
- Work on parking area delayed due to heavy rain.
- The building is now closed up at night to prevent unauthorized persons from entering the building.
Thursday, July 23
- Office flourescent light bulbs ordered.
- NS Power installing the main power transformer for the church.
- Dexter Construction is grading the driveway area in front of the church building.
Friday, July 24
- Dry wall taping on the second floor, in preparation for painting, is completed.